Short answer: Module A4 in the Swedish climate declaration (klimatdeklaration), which applies to new buildings in Sweden, is the climate impact of transporting construction products from the factory to the construction site. It must be calculated using climate data from Boverket's climate database (Boverkets klimatdatabas), either directly with the database's generic A4 values or with the project's own data on distance, transport mode or actual fuel consumption. The developer (byggherre) is responsible for the declaration, which must be registered with Boverket before the municipality can issue final clearance (slutbesked).
Since 1 January 2022, a climate declaration must be prepared when a new building is erected in Sweden. The requirement applies to buildings for which the building permit (bygglov) application was received by the municipal building committee (byggnadsnämnden) on or after 1 January 2022, under the Swedish Act (2021:787) on climate declarations for buildings. The declaration is registered with Boverket, the Swedish National Board of Housing, Building and Planning. If you build outside Sweden, check the local requirements.
The declaration covers the construction stage, that is, modules A1–A5 under the European standard EN 15978:
Several buildings are exempt, including buildings with a gross floor area of no more than 100.0 m², buildings for industrial or workshop purposes, agricultural and forestry buildings, buildings with a temporary building permit of no more than two years, and buildings erected by a private individual outside a business activity. The requirement applies only when new buildings are erected (Section 2 of the Act).
A4 covers the transport of the built-in construction products in three building parts: load-bearing structural elements, the building envelope and internal walls, from the manufacturer to the construction site. These are the same building parts that are included in A1–A3.
| Included in A4 | Not included in A4 |
|---|---|
| Transport of construction products in the structural frame, foundation, building envelope and internal walls | Transport of other construction products, such as building services installations and interior fittings |
| All legs from factory to site, for example via a builders' merchant or terminal | Transport of site huts and construction machinery to and from the site |
| Empty return trips, since they are included both in the database values and in actual fuel consumption | Transport of consumables |
| Transport of construction waste, which is reported under A5 construction waste |
For construction logistics, this means that far from all deliveries in the delivery calendar belong to A4. A delivery of precast concrete elements or facade boards does, but a delivery of site huts, scaffolding, tools or consumables does not.
Boverket's regulations (BFS 2021:7) state in Section 5 that generic climate data from Boverket's climate database must be used for transport to the construction site. Specific A4 values from a supplier's environmental product declaration (EPD) may not be used. What the project can replace instead is the transport data itself. Boverket describes three options:
| Option | Project's own data | Data from Boverket's climate database |
|---|---|---|
| 1. Actual fuel consumption | Fuel type and quantity consumed (litres or MJ), including the empty return | Conversion factor and climate data for the fuel |
| 2. Distance and transport mode | Distance per leg (km) and transport mode (for example truck, rail or ship) | Energy use per tonne-kilometre and climate data for the fuel |
| 3. Generic A4 value | Only the quantity of built-in product (kg) | The product's A4 value (kg CO2e per kg of product) |
Options 1 and 2 are called project-specific transport data. Climate data for fuel and energy must always be taken from Boverket's climate database. The database's energy values per tonne-kilometre are usually calculated for trucks and include empty returns.
Boverket points out that a transport chain with many legs is hard to verify, but that it is considerably easier to replace the generic A4 values when the delivery goes directly from factory to site. For composite products such as panel and volumetric elements, it is often simplest to use project-specific data.
Unlike the A1–A3 values for construction products, the transport and fuel climate data in the database are not set conservatively. The database is updated annually or as needed. The latest version, 02.07.000, was published on 21 January 2026. Always take current values from the database instead of reusing old ones.
EXAMPLE – invented quantities and distances. The factors (1 and 1.5 MJ per tonne-kilometre, 0.0757 and 0.0204 kg CO2e per MJ, and 0.0232 kg CO2e per kg of plasterboard) are taken from Boverket's own worked examples on the page "Indata för transport" (transport input data). Always use the values that apply in the current version of Boverket's climate database.
A project builds in 50 tonnes of plasterboard. It is driven 200 km by long-haul truck to a construction logistics terminal and then 15 km by local distribution truck to the site.
| Calculation | Working | Result (EXAMPLE) |
|---|---|---|
| Option 3, generic A4 value | 50,000 kg × 0.0232 | 1,160 kg CO2e |
| Option 2, diesel all the way | (50 × 200 × 1 × 0.0757) + (50 × 15 × 1.5 × 0.0757) | 757 + 85 = 842 kg CO2e |
| Option 2, HVO100 on the long leg | (50 × 200 × 1 × 0.0204) + (50 × 15 × 1.5 × 0.0757) | 204 + 85 = 289 kg CO2e |
The example shows two things. Project-specific data can give a lower figure than the generic value, but only if the distance is actually shorter than the database's assumption. And the choice of fuel and transport mode has a large effect on the result.
In practice, transport data comes from contractors and suppliers. Boverket gives the example of the developer requiring, already in the tender documents, that the contractor supply documentation and supporting evidence.
In May 2026, Boverket submitted a proposal to the Swedish Government to replace today's climate declaration with new requirements in the Planning and Building Act, in order to implement the EU Energy Performance of Buildings Directive (EPBD):
These are proposals, not rules in force. The consultation period ended on 23 October 2026 and the matter is now being prepared in the Government Offices of Sweden (Regeringskansliet). Levels and dates may change.
How much a measure shows in the declaration depends on the calculation method. With generic A4 values (option 3), only the quantity of material shows. With distance and transport mode (option 2), the choice of supplier, route, transport mode and fuel shows. With actual fuel consumption (option 1), load factor and empty running also show.
LogiPlan is a construction logistics system. In LogiPlan Site, contractors and suppliers book their deliveries in a shared delivery calendar with unloading zones, gates and resources. LogiPlan Terminal handles terminals and warehousing. For the climate declaration, LogiPlan collects transport data from the delivery bookings and calculates climate impact according to part A4 of the climate declaration, with searchable supplier addresses and automatic distance calculation. The statistics show CO2 and CO2e emissions for projects that have enabled emissions registration in delivery booking.
This gives you ongoing documentation during construction instead of collecting it after the fact. The developer is still responsible for the declaration and for making sure the right deliveries (construction products in the structural frame, foundation, building envelope and internal walls) are counted.
Want to see how it works in your project? Book a demo or email info@logiplan.se.
A4 is the climate impact of transporting construction products from the factory to the construction site. In the Swedish climate declaration, it covers the built-in products in load-bearing structural elements, the building envelope and internal walls.
No. Specific climate data from an EPD may not be used for A4. However, the project's own transport data, such as distance, transport mode or actual fuel consumption, may be combined with fuel climate data from Boverket's climate database.
No. Transport of site huts, construction machinery and consumables is not included in A4 of the climate declaration.
The developer (byggherre) is responsible for preparing it and registering it with Boverket, even if someone else does the calculation.
It must be registered with Boverket before the building committee can issue final clearance (slutbesked). Boverket recommends making the final calculation late so that it reflects the completed building.
New buildings in Sweden for which a building permit was applied for on or after 1 January 2022. Exemptions include buildings of no more than 100.0 m² gross floor area (BTA), industrial and workshop buildings, agricultural buildings, buildings with a temporary building permit of no more than two years, and buildings erected by private individuals outside a business activity.
Not today. Boverket has proposed limit values for the construction stage A1–A5 from 1 January 2030. The proposal was out for consultation until 23 October 2026 and has not been decided.
For five years from submission of the climate declaration.